Skip to content
Serving South & Central Florida, from Orlando to NaplesEspañol
Clear Line Environmental Solutions

Compliance guide

Commercial septic in Florida: DEP rules, sewer hookup and Connect 2 Protect

Florida's septic program has been run by DEP since July 1, 2021 [1]. If public sewer becomes available, a working system must connect within 365 days of the utility's written notice [3]. Once connected, the old system must be abandoned within 90 days under a permit: pumped out, then ruptured and filled, or removed [2].

Last reviewed 7 official sources

Clear Line vacuum truck parked under palm trees in South Florida

Key takeaways

  • DEP, not the Department of Health, has run the onsite sewage program since July 1, 2021 [1].
  • The rules are in Chapter 62-6, F.A.C., which used to be numbered 64E-6 [2].
  • Repairing, modifying or abandoning a septic system requires a DEP permit first [2].
  • Once a utility notifies you that sewer is available, a properly working system has 365 days to connect [3].
  • The old tank must be abandoned within 90 days of the sewer connection [2].
  • Miami-Dade's Connect 2 Protect includes a Commercial Corridors Program for more than 1,000 commercial properties [6].

At a glance

Regulator
Florida DEP, since July 1, 2021 [1]
Governing rule
Chapter 62-6, F.A.C. (formerly 64E-6) [2]
Connect after notice
365 days for a working system; 90 days if DEP has said it needs repair [3]
Abandon old tank
Within 90 days of connecting to sewer [2]
Who may pump
Service companies with an annual DEP operating permit [2]
Miami-Dade commercial funding
$126 million in GOB funds for commercial corridors [6]

Who regulates commercial septic systems now

Florida's onsite sewage treatment and disposal system program, which covers septic systems, moved from the Department of Health to the Department of Environmental Protection effective July 1, 2021 [1]. The transfer started with Senate Bill 712 in the 2020 session. The bill was signed into law on June 30, 2020, as Chapter 2020-150, Laws of Florida [1]. The Legislature calls that law the Clean Waterways Act [4].

In most counties, county health department staff stayed Department of Health employees but now run the program under DEP's direction [1]. DEP's transfer page lists the counties where permitting and inspections moved directly to DEP: 16 Panhandle counties and Marion County [1]. Miami-Dade, Broward and Palm Beach are not on that list, so expect the local health department office to still handle your file, applying DEP's rules. Confirm with your local office before you file anything.

The technical rules are in Chapter 62-6 of the Florida Administrative Code. Each rule's history note reads "Formerly 64E-6.0xx" [2], so an older document citing 64E-6 refers to the same requirements before renumbering. Use the current 62-6 text on flrules.org, because several rules have changed since the transfer. The abandonment rule, for example, was amended June 8, 2026 [2].

What Chapter 62-6 means for commercial owners

Most of Chapter 62-6 is about designing and installing new systems. The parts that matter to an owner of an existing commercial system are permits, who may pump it, and the rules for food operations.

Chapter 62-6 provisions relevant to existing commercial systems
TopicWhat the rule says
PermitsNobody may construct, repair, modify or abandon a system without first getting a system construction permit (Form DEP 4016) [2].
RepairsAn owner or lessee of a system that is improperly built or maintained, or not working safely, must request a repair permit before repairing it. The application is Form DEP 4015 [2].
Changes in useA system treating commercial wastewater must be brought fully up to current rules when sewage flow or waste strength increases [2].
Mixed sewageIf commercial and domestic sewage go into one system, all of it is treated as commercial sewage [2].
Food operationsCommercial and institutional food operations count as commercial sewage. Grease interceptors are required where grease could cause line stoppages or hinder sewage disposal [2].
Grease ahead of septicOnly kitchen wastewater goes through the interceptor, then into the septic tank's first compartment. Minimum interceptor volume is 750 gallons; any single chamber is 1,250 gallons at most [2].
PumpingA septic tank or grease interceptor may be cleaned only by a service company holding an annual DEP operating permit. Haulers keep collection logs for five years [2].

Adding a grease interceptor to an existing system as a precaution counts as a modification and needs a permit [2]. After a pump-out, the rule requires the original lid to be replaced, or a new one fitted if it is broken, and the lid sealed and secured [2]. Septage and food establishment sludge must go to an approved facility. Untreated sludge must not be spread on land [2].

Septic tank and drainfieldBuildingPumped through the access lidsScum (grease, light solids)Clarified effluentSludgeDrainfieldSludge and scum that reach the outlet clog the drainfield. Pumping removes them first.
Septic tank and drainfield. A conventional system: the tank settles solids and holds scum; liquid effluent flows to the drainfield.

When you must connect to sewer

Section 381.00655, Florida Statutes, sets the connection deadlines. They depend on the condition of your system and on when the utility tells you sewer is available.

Connection timing under s. 381.00655, F.S.
SituationDeadline or rule
Advance noticeAt least 1 year before sewer becomes available, the utility must notify you of the expected availability and that you will have to connect [3].
System working properlyConnect within 365 days of the utility's written notice that sewer is available [3].
System needs repair or modificationConnect within 90 days of written notice from DEP. In hardship cases DEP may grant one extension of no more than 90 days [3].
Connection chargesYou may prepay the amortized connection charges in equal monthly installments over up to 2 years from the first notice [3].
Investor-owned utility, hardshipThe local governing body may allow the connection fee to be paid without interest over up to 5 years, using its own hardship criteria [3].
WaiverThe utility may waive mandatory connection, with DEP approval, if connection is not required in the public interest due to public health considerations [3].

"Available" has a specific meaning in the law. The utility must be able to connect your plumbing, must not be under a DEP moratorium, and must have enough permitted capacity [4]. For an establishment with an estimated flow of 1,000 gallons per day or less, a gravity sewer line, or an approved low-pressure or vacuum line, must exist in a public easement or right-of-way that abuts the property [4]. Above 1,000 gallons per day, a sewer line, force main or lift station in a public easement or right-of-way counts if it abuts the property or is within 50 feet of the property line [4].

On property zoned or used for industrial or manufacturing purposes, DEP may not issue a construction permit for a septic system where public sewer is available [4]. On such property an existing system may be repaired only if sewer is not available within 500 feet of the building sewer stub-out [4].

The Clean Waterways Act in brief

Chapter 2020-150, the Clean Waterways Act, moved the septic program to DEP [1][4]. It also changed how DEP plans cleanups of polluted water bodies. Where DEP adopts a basin management action plan for a nutrient total maximum daily load, and finds that septic systems contribute at least 20 percent of the nutrient pollution, the plan must include a septic remediation plan [5]. That plan inventories septic systems and decides which will be connected to sewer, upgraded to nutrient-reducing systems, or left as they are. It also estimates costs and sets deadlines [5]. The law set July 1, 2025, as the deadline for adopting these plans [5].

For a property inside such a plan's area, the septic permit must follow the remediation plan or Chapter 62-6, whichever is stricter, and the application must say the lot is covered [2]. Whether a plan covers your parcel is a question for DEP or your local health department office. This guide does not say any South Florida plan applies to you.

Miami-Dade's Connect 2 Protect

Connect 2 Protect is the Miami-Dade Water and Sewer Department's multi-year, countywide program for extending sewer to properties on septic [7]. The county counts about 120,000 septic systems in use. It estimates about 9,000 are vulnerable to compromise or failure under current groundwater conditions, rising to about 13,500 by 2040 [6]. As groundwater rises, it reduces how well septic systems treat wastewater [7].

  • Commercial Corridors Program: $126 million in General Obligation Bond funds for more than 1,000 commercial properties along five commercial corridors, in 35 projects [6]. The county page says all were "anticipated to be completed by 2023". Ask WASD for the current status of your corridor [6].
  • Residential help: eligible homeowners with a Homestead Exemption can receive up to $15,000 in grants, or zero-percent or low-interest loans [6]. The county page does not describe a grant for commercial owners [6].
  • Ojus: owners in the Ojus area agreed to a Special Benefit Area, paying for the sewer through special assessments on their property tax bills over 30 years. The project converts 107 parcels [7].
  • Next steps listed by the county include public laterals for properties abutting sewer and a residential and commercial septic registration program [6].
  • Not sure whether you are on septic? For unincorporated areas the county points to its iWASD Connect GIS Viewer. In a city, contact the city's water and sewer department [6].
From septic to sewerBefore: on septicSeptic tankDrainfieldAfter: connected to sewerOld tank pumped out, thenremoved or filled in place(abandoned under permit)New service lateralPublic sewer mainStreet
From septic to sewer. Before: tank and drainfield. After: the building drains through a lateral to the public main, and the old tank is abandoned.
  1. 01

    Confirm your status

    Check whether you are on septic and whether sewer is planned or available, using the county's GIS viewer or your city utility [6].

  2. 02

    Read the notice

    Note the date on the utility's written notice. It starts your 365-day connection window [3].

  3. 03

    Get connection costs and permits

    Ask the utility for connection charges and payment options [3]. Hire a licensed plumber for the private-side connection. Our operational advice: get the plumbing permit requirements from your local building department.

  4. 04

    Book the abandonment

    Line up the abandonment contractor and permit: a DEP general permit (Form DEP 4011) or a system construction permit. If your utility or plumbing authority runs its own abandonment program, it may take the place of the DEP permit [2].

  5. 05

    Connect and pump out

    Once the building is connected, the tank is pumped by a permitted septage company, which gives the contractor a receipt or written certification [2].

  6. 06

    Abandon within 90 days

    The tank is ruptured or collapsed and filled with clean sand or similar material, or removed. Photos and a certification go to DEP [2].

Abandoning a septic tank the right way

Under rule 62-6.011, abandonment is done under a general permit or a system construction permit [2]. Under the general permit, the contractor files a notice of intent with the fee and the property, contractor and system details. DEP then issues the permit on Form DEP 4011. It is valid for 18 months [2].

  • Pump-out: a permitted septage disposal company empties the tank and gives the contractor a receipt or written certification. A tank already empty and dry needs a written statement saying so [2].
  • Rupture or collapse: the bottom is opened or ruptured, or the whole tank collapsed, so it cannot hold water [2].
  • Fill: the tank is filled with clean sand or other suitable material and covered with soil. A tank that cannot be ruptured or collapsed must be filled with flowable fill concrete [2].
  • Or remove: the tank may be taken off site instead, following the rule's procedure for spoil material. Under the general permit, a removed tank must be scrapped [2].
  • Photos: dated, located digital photos of the emptied tank, the fill going in, the filled location, and a landmark showing where it is on the property [2].
  • Close-out: the contractor certifies the work. Under the general permit, DEP inspects on site only if the paperwork is incomplete or suggests noncompliance [2].

Under a system construction permit, the application uses Form DEP 4015, and DEP or a private provider inspector must inspect the abandonment [2]. Tanks may stay in service only if DEP approves them as part of a Chapter 403-permitted system or a stormwater system [2]. Converting a tank into a cistern is limited to single-family residences [2].

Pump-out practice for commercial tanks while you wait

Miami-Dade asks owners waiting for sewer to keep maintaining their septic systems [6][7]. The rules above say who may pump and what happens to the waste. They set no pumping interval for a conventional commercial tank. The advice below is our operational guidance, not a rule.

  • Measure, don't guess: have sludge and scum checked at every visit and set the next date from what is found.
  • Busy sites (restaurants, schools, plazas on septic) often need pumping every 6 to 12 months; lightly used offices can go longer.
  • Keep grease out: pump the grease interceptor on its own schedule so fats never reach the septic tank.
  • Keep the paperwork: the hauler's pumping record is useful for any repair permit, sale or conversion.
  • Watch the drainfield in the wet season: high groundwater, which the county says peaks around September and October, makes problems more likely [6].
  • Don't put off a failing system because sewer is coming: if DEP notifies you that it needs repair, the 90-day connection deadline applies once sewer is available [3].
Rear of a Clear Line vacuum tanker with suction hoses mounted
Final pump-outs before abandonment are usually one visit with a high-capacity vacuum truck.

Key dates

  1. June 30, 2020

    Clean Waterways Act signed

    SB 712 becomes Chapter 2020-150, Laws of Florida [1].

  2. June 30, 2021

    Interagency agreement

    DOH and DEP sign the agreement for running the program [1].

  3. July 1, 2021

    Program moves to DEP

    DEP takes over the onsite sewage program from DOH [1].

  4. Late summer 2022

    Ojus construction

    Work on the Ojus sewer expansion begins, lasting about a year [7].

  5. July 1, 2025

    Plan deadline

    Deadline to adopt wastewater and septic remediation plans in nutrient basin management action plans [5].

  6. July 9, 2025

    Permit form updated

    Form DEP 4016, Construction Permit and Inspection, takes effect [2].

  7. June 8, 2026

    Abandonment rule amended

    Rule 62-6.011 amended; Form DEP 4011 general permit for abandonment effective June 2026 [2].

  8. 2040

    County projection

    Vulnerable septic systems in Miami-Dade projected to reach about 13,500 [6].

How Clear Line fits in

Clear Line and our Partner Network handle septic pumping, grease interceptors and line jetting, so you have one contact and one invoice. We do not issue permits, and the utility, your plumber and the abandonment contractor each handle their own part. This is where we usually help commercial owners going through a septic-to-sewer conversion:

  • Routine septic and grease interceptor pump-outs while you wait for sewer, with a pumping record each visit.
  • Scheduling the final pump-out before abandonment, timed to the contractor's schedule, and passing on the written pump-out record the contractor needs.
  • Hydro-jetting the building drain before or after the tie-in, to clear grease and scale that a new lateral would otherwise inherit.
  • A 24/7 line that sends the nearest crew from our network if the old system backs up or overflows during construction.

Septic-to-sewer checklist for commercial properties

  • Confirm whether the property is on septic and whether sewer is planned (county GIS viewer or city utility) [6]
  • File the utility's written availability notice and note the date: 365 days to connect [3]
  • Ask the utility for connection charges and the 2-year prepayment option [3]
  • Pull existing septic permits and pumping records for the file
  • If the site has a kitchen, confirm the grease interceptor is in place and on a pump-out schedule [2]
  • Hire a licensed plumber for the private-side connection
  • Choose the abandonment route: DEP general permit (Form DEP 4011) or system construction permit [2]
  • Schedule the final pump-out with a DEP-permitted septage company and keep the receipt [2]
  • Make sure the tank is ruptured or collapsed and filled, or removed [2]
  • Make sure dated, located photos and the contractor's certification go to DEP [2]
  • Finish abandonment within 90 days of connecting, and never reuse the old tank [2]
  • Hydro-jet the building drain if lines are slow before the tie-in

Frequently asked questions

Who regulates septic systems in Florida now?

The Florida Department of Environmental Protection, since July 1, 2021. The change came from SB 712, signed June 30, 2020, as Chapter 2020-150. In most counties, health department staff still run the program locally under DEP direction.

How long do I have to connect once sewer is available?

A properly working system must connect within 365 days of the utility's written notice that sewer is available. If DEP has notified you that your system needs repair or modification, you have 90 days, with one possible hardship extension of up to 90 days.

What counts as sewer being "available" for a business?

Up to 1,000 gallons per day, a gravity, low-pressure or vacuum line must exist in a public easement or right-of-way abutting the property. Above 1,000 gallons per day, a sewer line, force main or lift station abutting the property or within 50 feet of the property line counts.

What happens to the old septic tank after I connect?

It must be abandoned within 90 days, and further use is prohibited. Under a permit, a permitted septage company pumps it out. The tank is then ruptured or collapsed and filled with clean sand or similar material, or removed.

Is there county money for commercial conversions in Miami-Dade?

Miami-Dade says it is investing $126 million in General Obligation Bond funds in a Commercial Corridors Program for more than 1,000 commercial properties. The grants of up to $15,000 are for eligible homeowners with a Homestead Exemption. Ask WASD whether your corridor is included.

Can any company pump my commercial septic tank?

No. Under Chapter 62-6, a septic tank or grease interceptor can only be cleaned by a service company holding an annual DEP operating permit, and the waste must go to an approved facility.

My restaurant is on septic. Does the rule say anything about grease?

Yes. Grease interceptors are required where grease could cause line stoppages or hinder disposal. Only kitchen wastewater passes through the interceptor, then into the septic tank's first compartment. Minimum interceptor size is 750 gallons.

How often should a commercial septic tank be pumped while we wait?

The rules set no interval for a conventional commercial tank. In our experience, busy sites often need pumping every 6 to 12 months. Sludge and scum are measured at each visit to set your schedule.

Sources

Official sources. Bracketed numbers in the text point to this list.

  1. [1]Onsite sewage program transfer to DEP · Florida Department of Environmental Protection
  2. [2]Chapter 62-6, F.A.C. — Standards for onsite sewage treatment and disposal systems · Florida Administrative Code (flrules.org)
  3. [3]Section 381.00655, F.S. — Connection of existing onsite systems to central sewerage · The Florida Legislature
  4. [4]Section 381.0065, F.S. — Onsite sewage treatment and disposal systems; regulation · The Florida Legislature
  5. [5]Section 403.067, F.S. — Total maximum daily loads and basin management action plans · The Florida Legislature
  6. [6]Connect 2 Protect: septic-to-sewer program · Miami-Dade Water and Sewer Department
  7. [7]Connect 2 Protect: Ojus Sanitary Sewer Expansion fact sheet · Miami-Dade Water and Sewer Department

This guide summarizes public rules to help owners and managers. It is not legal advice. Rules change: always confirm with the agency that issues your permit.

Get a free quote

Florida rules for commercial septic: DEP permits, the 365-day sewer connection rule, Miami-Dade's Connect 2 Protect and how to abandon a tank properly.

Call 24/7Get a free quote